Super Heavy booster
Booster 22
Cryo Proof
- Type
- Booster
- Block
- TBD
- Current stage
- Cryo Proof
- Location
- TBD
- Facing
- TBD
- Milestones
- 4
Production timeline
- Cryo Proof09 SEP '26Completed first full cryogenic proof test at Massey Outpost.
- Stacking14 AUG '26Booster 22 completed stacking Aug 14 2026 — F:11 section stacked atop A:25 in Mega Bay 1.
- Stacking30 JUL '26B22 stacking underway in Mega Bay 1: LOX landing tank stacked into B22 on July 28-29, AX:2 aft section moved to MB1 on July 30.
- Spotted29 JUN '26Booster 22 (Block 3 Super Heavy) first spotted; aft dome section moved into Mega Bay 1.