Super Heavy booster

Booster 22

Cryo Proof
Type
Booster
Block
TBD
Current stage
Cryo Proof
Location
TBD
Facing
TBD
Milestones
4

Production timeline

  1. Cryo Proof09 SEP '26
    Completed first full cryogenic proof test at Massey Outpost.
  2. Stacking14 AUG '26
    Booster 22 completed stacking Aug 14 2026 — F:11 section stacked atop A:25 in Mega Bay 1.
  3. Stacking30 JUL '26
    B22 stacking underway in Mega Bay 1: LOX landing tank stacked into B22 on July 28-29, AX:2 aft section moved to MB1 on July 30.
  4. Spotted29 JUN '26
    Booster 22 (Block 3 Super Heavy) first spotted; aft dome section moved into Mega Bay 1.